Level 2: Detailed Linked Count
Level 2 Detailed Linked Count Description
A detailed linked count includes the following:
- application boundary is defined
- full functional decomposition to transaction level
- all files and transactions within scope are uniquely identified
- all files and transactions are classified according to type
- all files and transactions are accurately categorised according to complexity (DETs and FTRs are identified within IFPUG ranges where possible)
- all related files and transactions are linked (aids in assessing impact of change requests)
- explanatory notes are attached to files and transactions where necessary
- count is recorded and reported using the SCOPE Project Sizing Software® software repository tool
Level 2 Count Attributes
Detailed Linked Counts are:
- very detailed
- easily auditable
- accurate (within the limits of the FPA technique +/- 10%)
- very well documented
- easily maintained
Best suited for the following count purposes:
- benchmarking projects (new development and enhancement)
- detailed estimates
- project tracking
- as detailed baseline model for future detailed enhancement project counting
Issues:
- time intensive – counting rates up to 250 fps per day
- rarely cost effective for large, legacy application baseline counts
Pre-requisites:
- good to high quality system documentation
- data model
- full access to system experts
SCOPE and Level 2 Counts
Use the Range option when selecting the complexity of Processes and Data Groups in SCOPE and link Processes and Data Groups.